Pièce
PLANNING ESTIMATIF.pdf · 788 mots · du marché « Fourniture et installation d'un bâtiment modulaire informatique pour le SDIS des Landes », dossier de consultation officiel.
N° Mode Nom de la tâche SOUS TACHE Durée Début Fin Prédécesseurs 14 Sep 26 21 Sep 26 28 Sep 26 05 Oct 26 12 Oct 26 19 Oct 26 26 Oct 26 02 Nov 26 09 Nov 26 16 Nov 26 23 Nov 26 30 Nov 26 07 Déc 26 14 Déc 26 21 Déc 26 28 Déc 26 04 Jan 27 11 Jan 27 18 Jan 27 25 Jan 27 01 Fév 27 08 Fév 27 15 Fév 27 22 Fév 27 01 Mar 27
Tâche J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M
1 NOTIFICATIONS NC Lun 04/01/27
2 ORDRE DE SERVICE NC Lun 04/01/27
3 MOIS DE NC 25 jours Lun Ven
PREPARATION 04/01/27 05/02/27
4 TRAVAUX DE VRD NC 11 jours Lun 08/02/27Sam 20/02/27
5 TRAVAUX NC 11 jours Lun Sam
D'ELECTRICITE 08/02/27 20/02/27
6 ETUDES EXES DU NC 26 jours Lun Lun
MODULE 04/01/27 08/02/27
7 FABRICATTION 131 jours Lun Dim
MODULE 15/02/27 15/08/27
8 MONTAGE MODULE 131 jours Lun 15/02/27Dim 15/08/27
9 ESSAIS ET VISITE 2 jours Mer Jeu
TECHNIQUE 01/09/27 02/09/27
10 LIVRAISON MODULE 3 jours Lun 06/09/27Mer 08/09/27
11 RACCORDEMENTS ET 11 jours Lun Lun
MISES EN SERVICES 13/09/27 27/09/27
12 OPR 1 jour Lun 27/09/27Lun 27/09/27
13 FORMATIONS 1 jour Mar 28/09/27Mar 28/09/27
14 RECEPTIONS 1 jour Lun 04/10/27Lun 04/10/27
Projet : Projet1 Tâche Jalon Récapitulatif du projet Jalon inactif Tâche manuelle Report récapitulatif manuel Début uniquement Tâches externes Échéance Progression manuelle
Date : Ven 11/09/26 Fractionnement Récapitulative Tâche inactive Récapitulatif inactif Durée uniquement Récapitulatif manuel Fin uniquement Jalons externes Avancement
Page 1
01 Mar 27 08 Mar 27 15 Mar 27 22 Mar 27 29 Mar 27 05 Avr 27 12 Avr 27 19 Avr 27 26 Avr 27 03 Mai 27 10 Mai 27 17 Mai 27 24 Mai 27 31 Mai 27 07 Jui 27 14 Jui 27 21 Jui 27 28 Jui 27 05 Jul 27 12 Jul 27 19 Jul 27 26 Jul 27 02 Aoû 27 09 Aoû 27 16 Aoû 27 23 Aoû 27 30 Aoû 27 06 Sep 27 13 Sep 27 20 Sep 27 27 Sep 27 04 Oct 27
M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V
Projet : Projet1 Tâche Jalon Récapitulatif du projet Jalon inactif Tâche manuelle Report récapitulatif manuel Début uniquement Tâches externes Échéance Progression manuelle
Date : Ven 11/09/26 Fractionnement Récapitulative Tâche inactive Récapitulatif inactif Durée uniquement Récapitulatif manuel Fin uniquement Jalons externes Avancement